On October 9th, 2025, the Brazilian Electricity Regulatory Agency (ANEEL) issued Official Letter No. 552/2025-GDG/ANEEL (“Official Letter”) to the Brazilian Wind Energy Association (ABEEólica) and the Brazilian Photovoltaic Solar Energy Association (ABSOLAR), formally announcing that it will begin processing applications for authorization of co-located energy storage systems (“ESSs”).
A co-located ESS is a storage facility installed alongside a power plant. This system can absorb energy from the power plant itself or from the grid for later injection, internal consumption, or provision of services to the system.
With this measure, market participants will be able to integrate ESS into their plants, signaling ANEEL’s proactive approach to fostering the integration of this technology into the National Interconnected System (“SIN”) and reinforcing the prospects for greater operational flexibility and energy security.
Regulatory Context
The regulation for the deployment of ESS was subject to Public Consultation No. 39/2023, which remains pending due to a request for review of the process by Director Fernando Mosna.
One of the controversial points under discussion in the process is the contracting of grid use in both directions (load and generation) by the ESS, which could, in theory, be considered a form of “double charging” for grid usage.
Other topics related to ESS operations will be addressed in a new phase of discussions (expected to be subject to a new public consultation), including ESS operation in natural monopolies and specific remuneration mechanisms for this technology.
In parallel, there was an expectation of a Capacity Reserve Auction (“LRCAP”) focused on ESS procurement. Although the Ministry of Mines and Energy (“MME”) launched a public consultation on the matter in 2024, the auction was postponed due to the absence of regulation for these technologies and prioritization of other power supply sources.
Recent statements by the Minister of Mines and Energy indicate that the process will be resumed , with the publication of a ministerial ordinance expected by the end of 2025.
ANEEL’s Decision
Given the relevance of ESS for system operation and security—especially in light of curtailment impacts on renewable generators—and following communications among MME, ONS, EPE, and ANEEL, as well as existing requests already filed, the Agency decided to begin processing and authorizing co-located ESS projects.
How to Apply for Authorization of a Co-located ESS from ANEEL?
Authorization will be granted based on current legislation and applicable technical criteria. Interested developers must submit the following documents to ANEEL:
- General layout of the project, including the ESS polygon and restricted-interest network, from the plant’s collector substation to the connection point;
- Technical study estimating annual energy injection associated with the project, including expected operating profile, overall system efficiency, discharge power, storage capacity, technology description, and equipment specifications;
- Environmental license compatible with the technical characteristics of the project, including the storage system;
- Transmission System Use Agreement (CUST) or Distribution System Use Agreement (CUSD), accompanied by the access opinion or equivalent document;
- Executive Summary for authorization issuance (Model available here);
- Declaration of Compliance with Regulatory Requirements (Model available here).
ANEEL will accept justifications in case of difficulty in presenting any required documents.
ANEEL’s decision to begin authorizing co-located ESS represents a significant step toward consolidating this technology as a strategic component of Brazil’s power matrix. Although the definitive regulation is still pending, ANEEL’s openness to granting such authorizations signals a regulatory environment more receptive to innovation and modernization in the sector.
For interested agents, this is a concrete opportunity to contribute to the development of solutions that enhance efficiency, security, and flexibility within the SIN.
Our Energy and Infrastructure team at Veirano Advogados is closely monitoring this matter and remains available for further clarification on this and related topics.