REDATA: new tax incentives for data centers

Executive summary

Law No. 15,504, dated September 15, 2026, reinstituted the Special Taxation Regime for Datacenter Services (“REDATA”). The regime grants a tax relief on the domestic acquisition and importation of electronic components and Information and Communication Technology (“ICT”) products intended for the fixed assets of data center installation, modernization, or expansion projects in Brazil.

The benefit consists of the suspension of PIS/Cofins, PIS/Cofins-Import (federal social contributions), IPI (excise tax), and Import Duty, which is converted into a zero rate upon fulfillment of the counterpart obligations and incorporation of the asset into fixed assets. The estimated forgone revenue is approximately BRL 5.2 billion in 2026 and BRL 1 billion in each of the following two years.

The implementation of REDATA, however, still depends on supplementary regulations for its effective implementation, including with respect to the conditions for qualification and co-qualification and the rules governing the counterpart obligations set forth by law. From a regulatory standpoint, one of the main open issues concerns the fulfillment of the electricity demand through renewable or low-emission sources, particularly regarding the definition of eligible sources, the potential adoption of additionality criteria, and the treatment applicable to natural gas (including, as applicable, the possibility of thermoelectric projects relying on emissions offset mechanisms).

What is REDATA

Legal entities with a project for the installation, modernization, or expansion of data center services in Brazil may apply for qualification under REDATA (a broad concept encompassing cloud computing, high-performance computing, and training and inference of AI models).

There is also a co-qualification mechanism, available to industrial suppliers of ICT products with a contractual relationship to supply goods to the qualified entity (which ceases if the supply contract is terminated).

Eligibility requirements: federal tax compliance, no record in the Cadin (Federal Registry of Outstanding Obligations Owed to the Federal Public Administration), prohibition for Simples Nacional taxpayers, and qualification granted by the Federal Revenue Service (Receita Federal).

Benefits by tax

  • PIS/COFINS on revenue: only for products listed in an Executive Branch act.

  • PIS/COFINS-Import: same condition as above.

  • IPI: on importation or dispatch from the industrial establishment; does not apply to products manufactured in the Manaus Free Trade Zone listed in an Executive Branch act.

  • Import Duty: only for goods without equivalent domestic production and that are listed.

Imports may be carried out on behalf of a third party (indirect import operation). Furthermore, once issued, the acts listing the eligible goods may only be amended to include new goods (a significant legal certainty safeguard).

Required counterpart obligations

Cumulative commitments of the qualified entity:

  • 10% of actual supply allocated to the domestic market (through sale or free transfer to ICTs/government) — replaceable by an additional 10% investment in R&D&I.

  • 100% of electricity through supply contracts or self-production from generation based on renewable or low-emission sources, as provided by regulation.

  • Water Usage Effectiveness (“WUE”) ≤ 0.05 L/kWh, with annual measurement.

  • 2% of the value of products acquired under the benefit in R&D&I, with ICTs, educational institutions, or equivalent entities (a private centralizing fund is permitted).

  • Sustainability criteria set forth in the regulation, a public sustainability report, and an independent audit for the free transfer.

Regional advantage: projects in the North, Northeast, and Center-West regions have the domestic market and R&D&I commitments reduced by 20%; at least 40% of R&D&I resources shall be directed to these regions.

Non-compliance: payment of suspended taxes with interest and penalties, ex officio assessment with the penalty under Section 44 of Law No. 9,430/1996, suspension of benefits, cancellation of qualification after 180 days without remediation, extension of the restriction to the entire economic group, and a 2-year waiting period for re-enrollment.

Energy counterpart obligation: open regulatory issues

Despite requiring that the entirety of the data center’s electricity demand be met through supply contracts or self-production from renewable or low-emission sources, it delegates key implementation aspects to regulation, including:

  • Definition of “low emission” and potential requirements for emissions offset mechanisms: the regulation may establish the criteria for classifying certain energy sources, including natural gas and biomethane, as well as allow the use of carbon credits and carbon capture, utilization, and storage technologies (CCUS/CCS) for purposes of meeting the regime’s requirements.

  • Additionality criteria for contracted energy: Although the law does not establish an additionality requirement nor link the energy to new ventures, the topic may be subject to discussion during the regulatory process. Any imposition of a minimum percentage of energy from new projects must observe the limits of the regulatory authority and the obligation set forth in the legal text.

  • Content of the sustainability report: although the law requires the disclosure of a report containing, at a minimum, the Water Usage Effectiveness (WUE), the energy supply sources, and other sustainability indicators, the applicable parameters, methodologies, and additional information remain subject to regulation. In this context, ancillary obligations with operational and compliance impacts may be imposed on the regime’s beneficiaries.

Future regulation will play a decisive role in defining the effective eligibility and benefit maintenance requirements. Depending on the requirements that may increase established, particularly regarding low-emission criteria, additionality, and sustainability reporting, the implementation and operating costs of projects may be significantly directly affecting their economic competitiveness.

Interaction with the Tax Reform

  • There are no CBS or IBS incentives in the law: no reduced rate, no deemed credit, no specific regime.

  • A significant portion of the package is in PIS/Cofins, taxes to be extinguished at the end of 2026, with effects legally limited to December 31, 2026.

  • The IPI incentive loses practical reach starting in 2027, with the reduction of rates to zero, except for products with a similar product manufactured in the Manaus Free Trade Zone (a scenario already excluded by the law itself).

  • There is no compensation, preservation, offset, or substitution mechanism for incentives in the migration to CBS/IBS.

  • The Import Duty tends to be the benefit with the longest horizon, as it is not affected by the substitution under Constitutional Amendment 132/2023.

Any continuation of the benefits under the new system will depend on new legislation, for which there is no concrete prospect at present.

The state-level front: ICMS and Confaz

REDATA covers only federal taxes. The ICMS (State VAT), which represents the largest share of the sector’s tax burden, remains outside the regime and currently concentrates the market’s main demand:

  • Claim before Confaz: the sector is seeking an agreement (convênio) authorizing the states to reduce ICMS on data center equipment and components, as a complement to REDATA. The topic has not yet been assessed in detail by Confaz.

  • Estimated effect: the ICMS tax relief on equipment could theoretically exceed 20% (considering the NCM classification and ICMS rate in the states).

  • Legal obstacle: under Supplementary Law 24/1975, the benefit requires a convênio approved unanimously and ratified by the states. No state may grant it individually.

  • Existing operational issues: ICMS-DIFAL on equipment entry, non-recoverable credits on fixed assets, requirement for state tax registration and electronic invoices (NF-e) for asset transfers between sites, as well as the need for special regimes for physical delivery to third-party data centers.

Even if the convênio advances, the benefit will have a short horizon (though potentially substantial in monetary terms), as ICMS will be replaced by IBS between 2029 and 2032 — a factor that should be incorporated into project modeling.

Practical impacts

  • Short window: capturing PIS/Cofins and IPI requires obtaining qualification and completing acquisitions within 2026. The procurement timeline becomes a tax variable.

  • Net gain may be lower than it appears: under the non-cumulative regime, PIS/Cofins on fixed assets already generated credits; the actual advantage is improved cash flow. With the broad CBS/IBS credit, this differential tends to shrink, hence the need for case-by-case analysis.

  • EPC and supply contracts: defining who captures the tax savings and who assumes the recapture risk.

  • Energy and water become tax clauses: the energy supply structure, through supply contracts or self-production, from renewable or low-emission sources, and low water consumption cooling solutions, are no longer merely ESG commitments but become a requirement for the enjoyment of the tax benefit.

    • The energy and water supply structure of the enterprise must comply with the criteria to be defined by regulation, including with respect to the potential verification of additionality and the adoption of emissions offset mechanisms, such as Carbon Capture and Storage (CCS) or equivalent technologies.

    • Additionally, the regulation may also allow the classification of natural gas-fired thermoelectric plants as low-emission sources.

  • Most benefited sectors: colocation and hyperscalers, hardware manufacturers and integrators, telecom, renewable or low-emission energy generators and traders, construction and electrical infrastructure, with emphasis on projects in the N/NE/CW regions.

Risks

  • Regulatory: the effective enjoyment of the benefit depends on the regulation of the conditions and procedures for qualification, co-qualification, and verification of counterpart obligations, including the classification of low-emission sources.

  • Temporal mismatch: long-term commitments in exchange for benefits largely restricted to 2026.

  • State-level: the ICMS tax relief depends on unanimity at Confaz and should not be assumed as certain in CAPEX projections.

  • Interpretive: the coexistence of the five-year term in the caput of Article 11-J and the December 31, 2026 cutoff in the sole paragraph will require clarification (since a substantial part of the tax incentive will extinguish in the end of 2026, i.e., PIS/COFINS and IPI).

Recommendations

  • Map eligible CAPEX by NCM classification and identify what can be brought forward to 2026.

  • Begin preparing for qualification now (tax compliance, Cadin, contractual ties for co-qualification).

  • Model scenarios with and without PIS/Cofins and IPI after 2026, isolating the Import Duty as the more enduring component.

  • Adjust contracts to allocate tax savings and recapture risk.

  • Structure the governance of counterpart obligations, including with respect to the contracting and verification of energy sources, WUE, R&D&I, and the public sustainability report.

  • Monitor the Confaz agenda and review the project’s ICMS structure (DIFAL, special regimes, asset transfers, and state tax registrations).

  • Assess location in light of the 20% reduction in incentivized regions.

  • Monitor regulation, especially the list of eligible goods — which, once published, may only be expanded.

  • Review the energy supply structure and associated contracts to preserve flexibility for adaptation to subsequent rules on low emission, additionality, verification, and emissions mitigation.

The practical application of REDATA incentives and their interaction with the Tax Reform depend on an individualized analysis of each project and the operational structure of each company, considering the CAPEX profile, procurement timeline, tax calculation regime, location, energy supply structure, regulation applicable to counterpart obligations, and multi-year commitments.

The Veirano team is available to assess eligibility, quantify the net benefit under each transition scenario, and structure the qualification process.