The Normative Resolution No. 1,038/2022 (“REN“), which shall come into force on September 1, 2022, establishes the procedures and guidelines for the process of obtaining a generation authorization grant (outorga) without the access information requirement, applicable to requests filed until March 2, 2022.
We highlight the following new provisions of the REN:
(i) The grant requests with exemption of access information must include a liability statement, according to the form provided for in the REN.
(ii) The resulting grant will not include the authorization for installing the project’s restricted interest transmission structure.
(iii) The authorization for installing the restricted interest transmission structure is conditioned upon the submission of a special request to ANEEL, including the executed CUSD/CUST (connection contracts), along with other documents and technical information.
(iv) The projects with grant requests submitted until March 2, 2022 shall have a deadline for implementation of up to 54 months, with a possibility for extension, in case the applicable access document determines a longer implementation term.
Lastly, the REN establishes that the project’s connection is at the sole risk of the agent, and therefore no liability reduction or exclusion in connection with grid access risks shall apply.
Our Infrastructure and Energy team is at your disposal for further clarifications on this and related matters.