On October 24, 2025, the Ministry of Mines and Energy (“MME”) issued Ordinance No. 118/2025, establishing the guidelines and procedural framework for the 2026 Capacity Reserve Auction (“LRCAP 2026”). The auction will contract capacity from new and existing natural gas-fired thermal plants, existing coal-fired plants, and hydropower expansion projects.
The auction is scheduled for March 18, 2026. Compared to the draft previously submitted to public consultation, the final version introduces a few relevant changes, including:
- Elimination of Products A and B. For the 2026 and 2027 products, only gas-fired thermal plants connected to the gas transmission network will be eligible. From Product 2028 onwards, new and existing gas-fired plants will compete within the same product category, regardless of network connection.
- Introduction of new Products – “Thermal Capacity 2031” and “Hydropower Capacity 2031”, both to be negotiated simultaneously in the final bidding round.
- Removal of the explicit penalty of up to a 30% reduction in fixed revenue for non-compliance with ONS dispatch instructions.
- Inclusion of biogas-fired thermal plants as eligible projects when biogas is used as the primary fuel.
- Oil- and biodiesel-fired thermal plants are now governed by a separate regulation (MME Ordinance No. 118/2025).
Access our summary of the key provisions below:
Our Energy team remains available to assist in assessing the implications of the Ordinance and to support the definition of strategic approaches for participation in the LRCAP 2026.