Guidelines and Framework for the LRCAP 2026 – Natural Gas, Coal-Fired and Hydropower Plants

The Power Reserve Auction (LRCAP 2026) is scheduled for March 18, 2026, with project registration and qualification to be completed by November 14, 2025.

On October 24, 2025, the Ministry of Mines and Energy (“MME”) issued Ordinance No. 118/2025, establishing the guidelines and procedural framework for the 2026 Capacity Reserve Auction (“LRCAP 2026”). The auction will contract capacity from new and existing natural gas-fired thermal plants, existing coal-fired plants, and hydropower expansion projects.

The auction is scheduled for March 18, 2026. Compared to the draft previously submitted to public consultation, the final version introduces a few relevant changes, including:

  • Elimination of Products A and B. For the 2026 and 2027 products, only gas-fired thermal plants connected to the gas transmission network will be eligible. From Product 2028 onwards, new and existing gas-fired plants will compete within the same product category, regardless of network connection.
  • Introduction of new Products – “Thermal Capacity 2031” and “Hydropower Capacity 2031”, both to be negotiated simultaneously in the final bidding round.
  • Removal of the explicit penalty of up to a 30% reduction in fixed revenue for non-compliance with ONS dispatch instructions.
  • Inclusion of biogas-fired thermal plants as eligible projects when biogas is used as the primary fuel.
  • Oil- and biodiesel-fired thermal plants are now governed by a separate regulation (MME Ordinance No. 118/2025).

Access our summary of the key provisions below:

 

 

Our Energy team remains available to assist in assessing the implications of the Ordinance and to support the definition of strategic approaches for participation in the LRCAP 2026.