The first legal action against the planned June 27 auction relates to the ceiling set by the government for the variable unit cost (CVU) of the plants of approximately 1,700 reais/MWh (US$296/MW/h).
With the measure, the MME aimed to ensure fair power rates and meet the countrys environmental commitments.
“In short, the plants that commit to a shorter start-up time would be better qualified,” Maria João Rolim, a partner at law firm Rolim Goulart Cardoso Advogados, told BNamericas.
However, players whose projects had a CVU higher than the 1,700 real-limit sought, through injunctions in the superior court of justice (STJ), authorization to take part in the auction, arguing that the restriction harmed competitiveness and the diversity of energy sources.
(…)
In the first case, an injunction has already been granted, which has reimposed the higher CVU ceiling, initially provided for in the tender guidelines, of approximately 2,700 reais/MWh.
According to the companies, the MMEs decision to lower the CVU to around 1,700 reais/MWh amounted to an impediment to the participation of their projects, as they would need a higher CVU.
“In the second case, the request for an injunction has not yet been assessed, but the grounds are based on the lack of public consultation on the A-factor criterion,” Juliana Melcop, of law firm Veirano Advogados, told BNamericas.
She thinks it unlikely that the auction will be suspended, given the ruling halting the governments lowering of the CVU ceiling.
“In the case of the second lawsuit [Eneva], if an injunction is granted, the auction will certainly be suspended or postponed, because it will affect the formula used for the bid price. The formula should be re-evaluated for everyone, reopening the deadlines for registering the CVU with [federal energy research company] EPE,” said Melcop.
Click here to see the full article