As expected by dam entrepreneurs in Minas Gerais, Decree No. 48,759, dated January 5, 2024, amends Decree No. 48,078, dated November 5, 2020, and makes adjustments to the procedure for the analysis and approval of the Emergency Action Plan related to mining dams (“PAEBM”).
Regarding the duties and competencies of the entities involved in the approval of PAEBM, according to the new decree:
GMG-CEDEC gains the authority to (i) define criteria for the realization of periodic drills; (ii) conduct technical field visits, whenever necessary, to optimize the analysis of the PAEBM section under its competence; and (iii) establish criteria for increasing the Zone of Self-Salvage (“ZAS”).
The State Foundation for the Environment (“FEAM”) is responsible for approving studies on dam break and flood maps.
The Interdisciplinary Committee of the Emergency Action Plan (“CIPAE”) is created to optimize procedures related to the PAEBM, with its duties and operating procedures to be defined in its internal regulations, to be published within 90 days.
Regarding the material aspects of the third section of PAEBM, the decree stipulates:
(i) Actions to protect and mitigate environmental impacts must focus on the flood zone.
(ii) Actions to protect and minimize impacts on the sanitation system must encompass the “urban water capture system, including capture up to distribution.” The previous wording only covered impacts on “water capture stations.” Also, under this point, the new wording excluded the spatial delimitation of the “flood zone,” allowing for the requirement of sanitation actions beyond the flood zone.
(iii) The diagnosis and plans to be organized and maintained by the entrepreneur include (a) the qualitative and quantitative monitoring of surface and groundwater and sediment in water bodies; (b) the transport of tailings or waste to water bodies; (c) the characterization of soil quality; and (d) the characterization of wildlife and flora.
Regarding the PAEBM approval process, the decree establishes new deadlines and procedures, conditioning the issuance of environmental licenses to its integral approval. Among the new stages and deadlines that the entrepreneur should be aware of are:

The rejection of the PAEBM will result in the immediate suspension of environmental licenses, regardless of other civil, administrative, and criminal penalties.
Finally, the Decree establishes that PAEBMs that do not have the dam break studies and flood maps approved by 01/06/2024 will be evaluated considering the changes in procedures outlined in the decree.