Guidelines for transmission access rules enter public consultation, and ONS releases the steps and schedule for the 1st Access Season

The public consultation seeks contributions for the draft ordinance that regulates the Access Seasons of the National Transmission System Access Policy (PNAST). Registration for the 1st Access Season must take place between June 1, 2026 and June 15, 2026, and the competitive process between September 28, 2026 and October 8, 2026.

The Ministry of Mines and Energy (MME) has published Ordinance No. 901/2026, initiating a public consultation from March 2nd through March 31st to discuss the guidelines governing the Access Season under the National Policy for Access to the Transmission System (PNAST), pursuant to Decree No. 12,772/2025.

Yesterday, the National System Operator (ONS) released the stages and schedule for the 1st Access Season of 2026, which are subject to revision upon publication of the MME’s guidelines ordinance. The schedule is set forth in the table below:

​Stage ​Projected Date
​Publication of the Access Season Systematic ​04/30/2026
​Publication of the 1st Technical Note – Criteria and Assumptions ​04/30/2026
​Registration for the 1st Access Season ​06/01/2026 – 06/15/2026
​Registration Admissibility Period ​06/16/2026 – 06/30/2026
​Publication of the 2nd Technical Note – Available Capacity ​08/31/2026
​Competitive Process Period ​09/28/2026 – 10/08/2026

Background

PNAST amended the procedures for accessing the power grid (Rede Básica), affecting generators, self-producers, and free consumers seeking to obtain permanent access or to expand contracted usage amounts on the transmission system. The prior model, based on a first come, first served basis, has been replaced by a periodic timeframe coordinated by ONS, referred to as Access Seasons. Additional materials prepared by our team on PNAST are available here.

Below is the material prepared by our team related to the public consultation draft: