ANEEL opens Public Consultation for the Capacity Reserve Auction in the form of Power (LRCAP)

The contribution period will be between 02/27/2025 and 04/14/2025. The Notice is expected to be published on 05/22/2025, with the Auction remaining scheduled for 06/27/2025.

The National Electric Energy Agency (ANEEL) has launched Public Consultation No. 010/2025 through a documentary exchange process to gather contributions related to the documents for the 2025 Capacity Reserve Auction (LRCAP), scheduled for June 27.

The draft Notice is based on the 2021 Auction Notice, with specific adjustments to align with the Guidelines and Systematic Ordinances (MME Ordinances 96, 97, and 100 of 2025). Among the key updates, capitalization bonds were included as a financial guarantee option; the section on revocation or annulment procedures was revised to align with recent energy auction notices; and the Notice was also adapted to comply with the provisions of Law No. 14,133/2021, replacing the repealed Law No. 8,666/1993.

The following points deserve special attention:

  • Simplification of the Participation Guarantee deposit: BRL 30,000.00/MW for both energy sources;
  • Possibility of providing ancillary services, with revenue stacking from multiple sources;
  • Inclusion of a risk matrix clause, clearly outlining the risks to which the developer is exposed, such as potential operational restrictions imposed by National System Operator (ONS), the obligation to secure a connection to the National Interconnected System (SIN), and the obligation to maintain the operational independence of Generation Units (GUs) committed under the contract;
  • Hydropower plants whose concession expires before the start of supply will not be eligible to participate in the auction;
  • Extension of hydropower plant concessions will be assessed on a case-by-case basis, ensuring compensation for unamortized investments;
  • Definition of new capacity depends on the use of new electromechanical equipment or, at a minimum, equipment not committed to projects with an active concession at the time of registration completion with Energy Research Office (EPE). There was a divergence on this matter between the Rapporteur, Director Ricardo Tili, and the technical team. The technical team recommended that bidders provide a manufacturer’s guarantee stating that the equipment had never been used before, whereas the Rapporteur proposed accepting a self-declaration from agents confirming that the assets were not part of any plant with an active concession as of 2025.02.14;
  • Tax reform, as a rule, cannot be used to request economic-financial rebalancing, as it is considered a “transition between tax systems” rather than the introduction of new taxes. Additionally, the technical team argued that the reform has already been enacted, and the mere approval of its effective application would not trigger the relevant contractual provisions.

Regarding the Capacity Reserve Power Contract (CRCAP), the following points stand out:

  • The delivery obligation will be the Availability of Power committed in the Auction bid;
  • There will be two distinct CRCAP models, depending on the energy source (UTE and UHE);
  • Possibility of contracting by Generation Unit (GU), subject to (i) independent measurement between the contracted units and other existing generating units within the plant; and (ii) the inability to submit different bids per GU;
  • Applicable penalties under the CRCAP include:

 

 

Our Energy and Infrastructure team has prepared an infographic on the guidelines established by the MME for the LRCAP 2025. Access the material here.

We are available to review the documents submitted to the Public Consultation and assist in defining the best strategy for LRCAP 2025. We embrace challenges, valuing agility, efficiency, and results.